You are assisting the controller of Meridian Corp., a calendar-year public business entity, with the accounting for a new cloud-based procurement system. Meridian reports under U.S. GAAP. Review the contract, cost schedule, accounting policy memorandum, and project correspondence to determine the appropriate recognition, measurement, and presentation for the year ended December 31, 20X5.
Show answer and rationale
Rationale
The cloud agreement is a service contract, but qualifying implementation costs are capitalized.
- Meridian cannot take possession of or independently run the software, so the Cloud Hosting Agreement does not convey a software license.
- Of the $360,000 paid for the three-year hosting term, $120,000 is 20X5 hosting expense and $240,000 remains prepaid at December 31, 20X5.
Only configuration and interface coding qualify as capitalized implementation costs.
- The $60,000 configuration cost and $90,000 interface coding cost total $150,000; straight-line amortization is $20,000 and $30,000, respectively, leaving $40,000 and $60,000 unamortized.
- The Accounting Policy Memorandum requires the $50,000 total amortization in the hosting-fee income statement line; the $15,000 preliminary assessment, $30,000 manual data conversion, and $20,000 training costs are expensed in 20X5.
Traps in this case
Treating every necessary onboarding activity as an asset
- Necessity does not make manual data conversion or training capitalizable, so the project manager’s $200,000 software asset must be removed and replaced with $100,000 net implementation costs after $50,000 of immediate expense and $50,000 of amortization.
Expensing the hosting payment when paid
- The January 1 payment covers service through December 31, 20X7, leaving two years of prepaid hosting fees at the 20X5 year-end.