The City of Lakewood is preparing its December 31, 20X5 capital projects fund statements, budgetary comparison information, and governmental-activities conversion entries. The library project began during 20X5 and remains under construction. The CPA must reconcile the fund's modified-accrual records to the economic-resources and accrual basis used for governmental activities.
Show answer and rationale
Rationale
The library project is an expenditure in the capital projects fund but construction in progress in governmental activities.
- The fund reports $3,600,000 of construction expenditures, including the $200,000 unpaid retainage in contracts payable.
- Governmental activities capitalize the accepted work; because no part of the library was placed in service in 20X5, no depreciation begins.
Bond financing, budget variances, and fund balance follow different reporting rules.
- The fund reports the $5,000,000 bond principal and $150,000 premium as other financing sources, while governmental activities report both as debt, expense the $70,000 issuance costs, and accrue $100,000 of interest.
- Actual investment earnings of $30,000 exceed the $25,000 budget by a $5,000 favorable variance; ending fund balance is $1,710,000 cash less $200,000 payable, or $1,510,000.
Traps in this case
Treating unpaid retainage as unrecorded construction
- The Contractor Payment Certification includes the $200,000 retainage in accepted work, and the trial balance already records its payable.
Treating bond proceeds as governmental-activities revenue
- The Governmental Activities Debt Schedule requires a $5,150,000 bond liability, not financing revenue, and the fund’s omission of accrued interest does not eliminate the $100,000 accrual.
Subtracting purchase orders from ending fund balance
- The Finance Committee Minutes document a $1,200,000 assignment, which classifies fund balance without reducing its $1,510,000 total; lapsed encumbrances are not construction expenditures.