Costs must be incurred during performance
The award permits Project Delta supply costs from January 1 through December 31, 2025.
The nonprofit charged $12,000 for supplies delivered December 20, 2024 and paid February 10, 2025.
The file shows the supplies supported Project Delta and includes an invoice and receiving report.
Most people call the charge compliant because the nonprofit paid it during the award period.
That answer uses the payment date and misses the rule that costs must be incurred during the period of performance.
Payment and documentation do not decide compliance by themselves. The governing award and regulation must be identified first, then the transaction must be compared with each applicable condition.
Applicable requirements and transaction evidence
The criteria below identify the requirements and the evidence needed to test a Federal award transaction. They follow the sequence for reaching a compliance conclusion.
- Identify the applicable compliance requirements. AU-C 935 describes these as requirements imposed by laws, regulations, and provisions of contracts or grant agreements applicable to the entity.
- Use effective internal control over the Federal award that provides reasonable assurance that the entity is managing the award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. Cite 2 CFR 200.303(a). This is the control setting, not a substitute for transaction evidence.
- Confirm that the Federal award is charged only for costs incurred during the period of performance. Cite 2 CFR 200.309.
- For a cost, confirm that it is necessary and reasonable for performance of the Federal award and allocable thereto. Cite 2 CFR 200.403(a).
- Confirm that the cost conforms to limitations or exclusions in the cost principles or Federal award. Cite 2 CFR 200.403(b).
- Confirm consistent policies and consistent treatment under 2 CFR 200.403(c)-(d).
- Confirm that the cost is determined in accordance with GAAP and is not included as a cost or used to meet cost sharing or matching requirements of another federally financed program. Cite 2 CFR 200.403(e)-(f).
- Confirm that the cost is adequately documented. Cite 2 CFR 200.403(g).
The evidence work resembles Estimates and fair value measurement and Inventory existence and condition: identify the governing requirement, inspect support, and compare the facts. Federal award testing differs because the governing requirements come from laws, regulations, and award terms.
🔑 RULE: All applicable requirements are tested in sequence; one failed applicable requirement creates a transaction exception.
One failed condition creates an exception
The flowchart shows where testing starts, where a failed condition ends the analysis, and how all applicable conditions lead to compliance.
Litigation, claims and legal letters relies on outside evidence, while this path starts with the applicable federal requirements. Going concern focuses on future plans and reporting effects; this path ends with a transaction exception when a condition fails.
Loading diagram…
A single failed applicable condition stops the transaction from reaching the compliance conclusion.
Supplies incurred before performance period
The table compares each fact with the condition it affects. The verdict appears only after the applicable conditions have been considered together.
| Fact | Criterion it touches | Met? |
|---|---|---|
| The award permits Project Delta supply costs during January 1 through December 31, 2025. | Applicable award term and cost limitation | Yes |
| The $12,000 supplies were delivered, and the cost was incurred, on December 20, 2024; payment occurred February 10, 2025. | 2 CFR 200.309, period of performance | No |
| The supplies supported Project Delta and were necessary for the award. | 2 CFR 200.403(a), necessary, reasonable, and allocable | Yes |
| The invoice and receiving report support the charge. | 2 CFR 200.403(g), adequately documented | Yes |
| Verdict: The $12,000 charge is not compliant and is a transaction exception. The wrong answer came from using the payment date instead of the incurred date. | Combining rule and period of performance | No |
The charge passes necessity, award fit, and documentation, but the incurred date fails the period-of-performance condition.
Equipment approval was required
The table applies the same sequence to an equipment purchase. Each verdict remains open until the award-specific approval term is tested.
| Fact | Criterion it touches | Verdict |
|---|---|---|
| The award period is January 1 through December 31, 2025. | Period of performance | ? |
| The nonprofit bought $9,000 of necessary Project Delta equipment on March 15, 2025. | Period and necessary, reasonable, allocable cost | ? |
| The invoice, receiving report, and use record are present. | Adequate documentation | ? |
| The award requires written approval for equipment purchases over $8,000, and no written approval was obtained. | Award limitation or approval term | ? |
| Verdict | All applicable requirements | ? |
The transaction passes timing, necessity, and documentation, but the award-specific approval term still applies.
Practice
What is the correct compliance conclusion for the equipment transaction?
Period, allocability, duplicate funding, wages
These cases change the failed condition. The choices distinguish period, allocability, duplicate funding, and a statutory wage requirement.
Practice
A Federal award runs from July 1, 2025 through June 30, 2026. A necessary and allocable $4,000 software license was provided on June 15, 2025, invoiced July 5, 2025, and paid July 20, 2025. The invoice and service record are complete. What is the correct conclusion?
An award runs from January 1 through December 31, 2025. A $7,000 renovation was incurred during that period and has a complete invoice, approval, and payment record, but it improved a separate department and did not benefit the awarded project. What is the correct conclusion?
The same $6,000 of salary was charged to the current Federal award and also used as matching support for another federally financed program. Timesheets support the salary and both awards are active during the proper period. What is the correct conclusion?
A construction award is subject to the Davis-Bacon Act. A worker's payroll transaction covers 40 hours at $18 per hour, while the applicable wage determination requires $22 per hour. The payroll record is complete and the work was performed during the award period. What is the correct conclusion?
Delivery during performance period
Was: The award permitted Project Delta supply costs from January 1 through December 31, 2025, and the nonprofit charged $12,000 for necessary, documented supplies delivered December 20, 2024 and paid February 10, 2025.
Now: Keep every fact the same, but the supplies were delivered January 20, 2025 instead of December 20, 2024.
Answer: The verdict changes to compliant. The period-of-performance criterion moved from not met to met; necessity, award fit, and documentation stayed met.
Only the incurred date moved, so only the period criterion changed. The payment date did not move and still does not control the conclusion.
Every applicable requirement must be met
- Identify every applicable statute, regulation, and award term.
- Charge only costs incurred during the period of performance.
- Require costs to be necessary, reasonable, and allocable.
- Follow award limitations, exclusions, and approval terms.
- Apply consistent policies and treatment, GAAP, and the no-duplicate-funding rule.
- Keep the transaction adequately documented.
All applicable requirements must be met. One failed applicable requirement creates an exception.
The commonly skipped criterion is mapping the award-specific terms before reviewing the transaction file.