Reconciling actual processing to approved documents
ERP and accounting systems and Risks of new technology and process change supply the system and change-risk context. These rules compare approved documents with evidence before judging controls.
- An ERP integrates business processes and shared data. An accounting information system captures, processes, and reports transaction data. Use these roles to identify records that should agree.
- An automated or changed step can create a new risk or leave approved documentation stale. Compare the performed step and its control with the approved design.
- The actual process must agree with its flowcharts, diagrams, and narratives. Name and resolve every difference.
- Processing integrity means system processing is complete, valid, accurate, timely, and authorized.
- AICPA Trust Services Criterion PI1.2 requires policies and procedures over system inputs.
- AICPA Trust Services Criterion PI1.3 requires policies and procedures over system processing.
- AICPA Trust Services Criterion PI1.4 requires policies and procedures over system outputs.
Northstar's March 2025 review is chapter 3 of 3 and takes 35 minutes. A new automatic retry runs at 23:30, but the approved flowchart ends at 23:00. Is this a documentation mismatch, a processing control issue, or both?
Comparing documented and actual process steps
| Process point | Narrative on prepared sheet | Flowchart box on prepared sheet | Actual evidence |
|---|---|---|---|
| Input checks | Credit check, then validate customer ID, item, and quantity | Credit check → input validation | Input validation at 08:00; credit check at 08:01 |
| Approval | Manager approval required when order total is greater than $5,000 | Manager approval required for every order | In a 40-order trace, 24 orders at or below $5,000 had no approval; 16 orders above $5,000 had approval |
| General-ledger posting | One nightly batch at 23:00 | One nightly batch at 23:00 | Normal batch at 23:00; automatic retry at 23:30 for failed rows |
| Exception report | Controller reviews the report every day | Controller reviews the report every day | Sign-off is present for 28 of 30 report dates; the prepared status says complete |
| Source record | Detail |
|---|---|
| Input-control test | 40 orders tested; 37 had complete customer ID, item, and quantity; 3 orders missing customer ID were accepted |
| Invoice register | 100 invoice records totaling $218,000 |
| General-ledger batch | 101 invoice records totaling $220,000; invoice INV-1044 appears twice, and the duplicate is $2,000 |
| Exception-report log | 30 report dates; 28 signed reviews; March 12 and March 25 have no sign-off |
Separating documentation mismatches from control deficiencies
A documentation mismatch is not automatically a processing-integrity deficiency. A control that accepts invalid input, posts an incorrect duplicate, or lacks required output review is a control exception under the applicable PI criterion.
| Problem and location | Correct figure or treatment | Rule that says so | Error tag |
|---|---|---|---|
| The input sequence in the narrative and flowchart is reversed. The event log shows validation at 08:00 and credit check at 08:01. | Change both documents to show input validation before the credit check. Retain the event log as evidence. | Actual steps must reconcile to narratives and flowcharts. | cross-document reconciliation |
| The flowchart applies manager approval to every order. The narrative requires it only above $5,000. | Require approval only above $5,000. The 24 orders at or below $5,000 do not need approval. The 16 orders above $5,000 do. | Use the approved process rule when reconciling the process to the diagram. | rule selection |
| The narrative and flowchart omit the automatic retry at 23:30. | Add the retry as a performed step. Document duplicate prevention or reconciliation before reposting. | An automated process change can introduce risk or make documentation stale. | fact extraction |
| The prepared PI1.2 conclusion says 40 of 40 input tests passed. Three orders missing customer ID were accepted. | Report 37 passing tests and 3 exceptions. Record a PI1.2 control exception. | PI1.2 requires policies and procedures over system inputs. | response entry |
| The prepared PI1.3 conclusion says 100 records and $218,000 agree. The batch has 101 records and $220,000. | Remove or correct duplicate INV-1044. Reconcile 101 records and $220,000 to 100 records and $218,000. | PI1.3 requires policies and procedures over system processing. | calculation |
| The prepared PI1.4 conclusion says daily output review is complete. Only 28 of 30 dates have sign-off. | Report 28 completed reviews and 2 missing reviews. The missing dates are March 12 and March 25. | PI1.4 requires policies and procedures over system outputs. | response entry |
The first three rows repair process descriptions. The last three rows show PI1.2, PI1.3, and PI1.4 control exceptions.
Reconciling process evidence and accounting differences
The smaller worksheet contains three planted errors.
| Record | Prepared process or control statement | Evidence excerpt |
|---|---|---|
| Input sequence | The flowchart shows input validation after the credit check | Event log: input validation at 08:00; credit check at 08:01 |
| GL tie-out | The batch agrees with the invoice register at 100 records and $218,000 | Invoice register: 100 records and $218,000; GL log: 101 records and $220,000, including duplicate INV-1044 |
| Output review | Daily controller review is complete for 30 of 30 dates | Sign-off log: 28 signed dates; March 12 and March 25 are blank |
Keep the invoice register at $218,000, but suppose the GL has 99 records totaling $216,000 because one $2,000 invoice was omitted. What signed adjustment reconciles the GL to the register?
Practice
The worksheet says the flowchart places input validation after the credit check. The event log shows input validation at 08:00 and the credit check at 08:01. Which item should be changed?
Change one fact: the GL contains 99 records totaling $216,000 because one $2,000 invoice was omitted. Using the invoice register as the base, what signed adjustment reconciles the GL amount to the register?
Two daily controller sign-offs are missing, but the invoice and GL data agree after the duplicate is removed. What is required for the missing sign-offs?
Comparing process order, totals and evidence
- Compare the performed order with every narrative, flowchart, and diagram. Do not let one matching document hide another mismatch.
- Reconcile both counts and amounts. Trace each unexplained difference to a specific input or processing event.
- Enter a control exception when required evidence is missing. Record a journal entry only when an accounting error is identified.
Unlock the full lesson and continue reading