Manufacturing overhead belongs in product cost
Job 17 uses $18,000 of direct materials and $12,000 of direct labor.
The labor is 600 direct-labor hours.
Factory estimates are $90,000 of overhead and 3,000 direct-labor hours.
Job 17 produces 100 units.
Many people answer $300 per unit, but that is wrong because it leaves out applied overhead.
Direct materials and direct labor are traced to the job. Manufacturing overhead must also be assigned. Cost behavior and absorption versus variable costing separates this assignment issue from fixed-versus-variable cost classification.
The next rule assigns overhead and selects the correct costing method.
Production pattern, costing method, overhead assignment
The criteria below come from managerial cost-accounting practice and the AICPA BAR objective. No authoritative percentage threshold selects one method.
🔑 RULE: First identify the production pattern, then choose job order or process cost accumulation, then choose a broad overhead rate or ABC pools and drivers.
- FASB ASC 330-10-30-1 states: “Inventory costs include all costs of purchase, costs of conversion, and other costs incurred in bringing the inventories to their existing location and condition.” Direct materials, direct labor, and allocated manufacturing overhead belong in product cost when they meet this boundary.
- Job order costing accumulates costs by separately identifiable job. Trace direct materials and direct labor to that job. Apply manufacturing overhead using a predetermined overhead rate.
Predetermined overhead rate = estimated manufacturing overhead ÷ estimated allocation base.
Total job cost = direct materials + direct labor + applied overhead.
Unit cost = total job cost ÷ units in the job. - Process costing accumulates costs by process or department for a period. Assign costs to units using equivalent units of production. For weighted average, combine beginning and current costs. Divide by total equivalent units for each cost component. For FIFO, use only current-period work: work needed to finish beginning work in process, units started and completed, and equivalent ending work in process.
- Activity-based costing identifies the major activities that consume resources. Assign resource costs to activity cost pools. Determine a cost driver for each pool. Compute a rate for each driver. Assign overhead based on each product’s consumption of those drivers. Use ABC when products consume overhead activities differently enough that one broad driver would distort product costs. No percentage cutoff is prescribed.
- The criteria combine sequentially. Choose job order for separately identifiable custom jobs. Choose process for homogeneous units made continuously. Then use ABC within either system when multiple activities explain overhead consumption.
This is cost assignment, not the fixed-versus-variable classification covered in Cost behavior and absorption versus variable costing. Cost variances and price-volume-mix analysis addresses later actual-versus-applied differences and cost drivers.
Job order, process, and ABC selection
The flowchart first selects job order or process accumulation. It then tests whether one broad rate is enough or whether ABC drivers are needed.
Loading diagram…
ABC can overlay either job order or process costing. It is an overhead assignment method, not a replacement for cost accumulation.
Job 17 total and unit cost
The table traces each fact through the job order conditions before calculating the final unit cost.
| Fact | Criterion it touches | Met or not met |
|---|---|---|
| Job 17 is a separately identifiable custom order. | Job order accumulation condition | Met |
| Direct materials are $18,000 and are traced to Job 17. | Direct material tracing | Met |
| Direct labor is $12,000 for 600 direct-labor hours. | Direct labor tracing and allocation base | Met |
| Estimated manufacturing overhead is $90,000 and estimated direct-labor hours are 3,000. | Predetermined overhead rate | Met |
| The rate is $30 per direct-labor hour, so applied overhead is $18,000. | Overhead assignment | Met |
| Job 17 has 100 units. | Unit cost calculation | Met |
| Verdict: total job cost is $48,000 and unit cost is $480. | All job order criteria; the $300 answer omitted applied overhead. | Met |
The rate is $90,000 divided by 3,000 hours. Job 17 receives $18,000 for its 600 hours. The $300 answer skips applied overhead.
ABC pool rates and Product X overhead
Each activity pool receives its own driver rate. The table checks whether Product X meets each ABC condition.
| Fact | Criterion it touches | Verdict |
|---|---|---|
| The plant has setup, inspection, and machine activities with separate overhead pools. | Identify activities and cost pools | ? |
| The pool costs are $60,000, $30,000, and $30,000. | Assign resource costs to pools | ? |
| The pool activity levels are 60 setups, 300 inspections, and 6,000 machine hours. | Determine driver rates | ? |
| Product X uses 10 setups, 20 inspections, and 400 machine hours. | Assign overhead based on driver consumption | ? |
| Product X’s overhead assignment and method. | ABC combining rule | ? |
Practice
What is the correct verdict for Product X?
The setup rate is $1,000 per setup. The inspection rate is $100 per inspection. The machine rate is $5 per machine hour. Product X receives $10,000, $2,000, and $2,000.
Jobs, equivalent units, and activity drivers
These questions apply the method to custom production, job order costing, FIFO equivalent units, and weighted-average process costing.
Practice
A manufacturer makes custom machines for different customer orders, traces materials and labor by order, and has setups, purchasing, and inspections that differ by order. Which method combination best fits?
Using Job 17’s facts, what is the total job cost?
Under FIFO process costing, what is the cost of ending work in process?
Under weighted-average process costing, what cost is assigned to the 800 completed units?
The calculations use a job, an equivalent unit by process, or an activity driver as the cost unit.
Continuous production requires process costing
Was: Job 17 is a separately identifiable custom order with $18,000 of direct materials, $12,000 of direct labor for 600 direct-labor hours, estimated overhead of $90,000 based on 3,000 direct-labor hours, and 100 units.
Now: Production is identical and continuous for inventory. Does the verdict change?
Answer: Yes, the method changes from job order costing to process costing because output changes from separately identifiable jobs to homogeneous continuous units. The direct materials, labor, and overhead facts do not change, but the production-pattern criterion does.
The changed fact affects method selection before arithmetic begins. Process costing then uses equivalent-unit calculations for the assigned costs.
Choosing job order, process, or ABC
Job order costing applies to separately identifiable jobs. Trace direct costs to each job and apply overhead with a predetermined rate.
Process costing applies to homogeneous units made continuously. Accumulate costs by department and use equivalent units.
Activity-based costing identifies activities, builds pools, calculates driver rates, and assigns overhead by resource consumption.
The combining rule is sequential. Production pattern selects job order or process. Overhead consumption selects one broad rate or ABC. ABC can overlay either system.
The skipped criterion is the overhead driver. Check whether different products consume activities differently.
Product-cost classification is separate from Cost behavior and absorption versus variable costing. Later actual-versus-applied differences connect to Cost variances and price-volume-mix analysis.