Actual and standard variance bases
The rules give each number a fixed base. Price or rate uses actual inputs. Usage or efficiency uses standard inputs allowed. The sales bridge uses the budget mix.
- Standard input allowed equals the standard input per unit multiplied by actual output. A cost variance compares actual cost with standard cost allowed for that output.
- A cost price or rate variance uses actual input quantity or hours multiplied by actual price or rate minus standard price or rate. Actual cost above standard is unfavorable, or U. Actual cost below standard is favorable, or F.
- A cost usage or efficiency variance uses standard price or rate multiplied by actual input quantity or hours minus standard input allowed.
- Variable costs change with activity within the relevant range. Fixed costs stay constant within that range. This rule comes from Cost behavior and absorption versus variable costing.
- Under absorption costing, fixed manufacturing overhead is assigned to units through an application rate. Fixed overhead therefore has a budget variance and a volume variance. This rule comes from Cost behavior and absorption versus variable costing.
- A cost driver is the activity that causes a cost. Use the activity that best explains the cost. Activity cost pools and drivers come from Job order, process and activity-based costing.
- Sales price variance equals actual units multiplied by actual price minus budget price.
- Sales volume variance equals actual total units minus budget total units, multiplied by the budget weighted-average price.
- Sales mix variance equals the sum of actual product units minus flexed product units, multiplied by each product’s budget price.
- Flexed units use actual total units in the budget mix.
- Price, volume, and mix variances must reconcile to actual sales minus budget sales.
- No universal investigation cutoff is supplied. Use a stated management threshold when one is given. Do not invent one.
- A variance report does not require a journal entry when the underlying ledger facts are correct.
The prepared report does not tie
The sales chart shows the prepared bridge before correction. The bars expose where the reported sales path separates from the actual source.
Loading diagram…
The bridge does not reach the actual source sales.
Prepared by the cost analyst; it does not tie.
The prepared cost report compares standard or budget amounts with actual amounts. Its labels and figures remain unchanged.
| Line | Standard allowed or budget | Actual | Prepared variance |
|---|---|---|---|
| Direct materials price | 21,000 kg at $5 = $105,000 | 21,000 kg at $5.20 = $109,200 | $4,000 U |
| Direct materials quantity | 20,000 kg at $5 = $100,000 | 21,000 kg at $5.20 = $109,200 | $5,000 F |
| Direct labor rate | 9,500 hours at $20 = $190,000 | 9,500 hours at $21 = $199,500 | $9,500 U |
| Direct labor efficiency | 10,000 hours at $20 = $200,000 | 9,500 hours at $21 = $199,500 | $10,000 U |
| Variable overhead spending | 9,500 hours at $4 = $38,000 | 9,500 hours at $4.20 = $39,900 | $1,900 U |
| Variable overhead efficiency | 10,000 hours at $4 = $40,000 | 9,500 hours at $4.20 = $39,900 | $2,000 F |
| Fixed overhead budget | $60,000 budget | $58,000 actual | $2,000 U |
| Fixed overhead volume | $50,000 applied | $58,000 actual | $10,000 U |
| Total cost variance | $390,000 standard allowed | $406,600 actual | $16,600 F |
The cost report contains incorrect signs and labels even where some amounts are correct.
The prepared sales report separates price, volume, and mix effects. Its bridge and total remain unreconciled.
| Line | Budget or flexed amount | Actual amount | Prepared result |
|---|---|---|---|
| Product A price | 7,000 units at $50 = $350,000 | 7,000 units at $48 = $336,000 | $14,000 U |
| Product B price | 5,000 units at $80 = $400,000 | 5,000 units at $75 = $375,000 | $25,000 U |
| Total price variance | $620,000 budget sales | $711,000 actual sales | $39,000 U |
| Sales volume variance | 10,000 budget units to 12,000 actual units at $62 = $124,000 | - | $124,000 F |
| Sales mix variance | Flexed A 7,200 units and B 4,800 units | Actual A 7,000 and B 5,000 | $6,000 U |
| Total sales variance | $620,000 budget sales | $711,000 actual sales | $79,000 F |
The sales report has the correct price amount but incorrect signs and bridge totals.
The source facts provide the inputs needed to test each prepared line.
| Area | Budget or standard facts | Actual facts |
|---|---|---|
| Output | 10,000 units | 10,000 units |
| Direct materials | 2 kg per unit at $5 per kg | 21,000 kg at $5.20 per kg |
| Direct labor | 0.5 hour per unit at $20 per hour | 9,500 hours at $21 per hour |
| Variable overhead | 0.5 hour per unit at $4 per hour | 9,500 hours at $4.20 per hour |
| Fixed overhead | $60,000 budget and $5 application rate per unit | $58,000 actual |
| Product A sales | 6,000 units at $50 | 7,000 units at $48 |
| Product B sales | 4,000 units at $80 | 5,000 units at $75 |
The source facts show the bases needed for price, efficiency, fixed overhead, and sales mix calculations.
Correct variance bases and cost drivers
Each correction uses the base that caused the variance. Price uses actual input. Quantity or efficiency uses standard price. Sales mix compares actual units with flexed budget units.
| Problem | Where it sits | Correct figure or treatment | Rule or chapter | Likely cost or sales driver | Error tag |
|---|---|---|---|---|---|
| Direct materials price variance | Cost report, direct materials price row | $4,200 U, calculated as 21,000 kg multiplied by $0.20 | Cost variances and price-volume-mix analysis | Supplier price, purchase timing, or material quality | calculation |
| Direct materials quantity variance | Cost report, direct materials quantity row | $5,000 U, calculated as $5 multiplied by 1,000 excess kg | Cost variances and price-volume-mix analysis | Waste, defects, or production method | response entry |
| Direct labor efficiency variance | Cost report, direct labor efficiency row | $10,000 F, calculated as $20 multiplied by 500 hours below standard | Cost variances and price-volume-mix analysis | Training, process time, or labor productivity | response entry |
| Fixed overhead budget variance | Cost report, fixed overhead budget row | $2,000 F, because actual fixed overhead of $58,000 is below the $60,000 budget | Cost behavior and absorption versus variable costing; Cost variances and price-volume-mix analysis | Fixed spending control | response entry |
| Total cost variance | Cost report, total row | $16,600 U, because actual cost of $406,600 exceeds standard allowed cost of $390,000 | Cost variances and price-volume-mix analysis | Combined material, labor, overhead, and capacity effects | cross-document reconciliation |
| Sales mix variance | Sales report, mix row | $6,000 F: A is 200 units below its flexed 7,200 units, giving $10,000 U; B is 200 units above its flexed 4,800 units, giving $16,000 F | Cost variances and price-volume-mix analysis | Product mix and customer demand | response entry |
| Total sales variance | Sales report, total row and bridge endpoint | $91,000 F, equal to $711,000 actual sales minus $620,000 budget sales; the bridge must end at $711,000 | Cost variances and price-volume-mix analysis | Price, total volume, and product mix together | cross-document reconciliation |
The corrected signs and totals make both reports tie to their source documents.
Corrected cost and sales totals
The cost schedule checks each component and then reconciles the total with actual cost. The sales schedule moves from budget sales through price, volume, and mix effects.
| Corrected cost schedule | Amount |
|---|---|
| Direct materials price variance | $4,200 U |
| Direct materials quantity variance | $5,000 U |
| Direct materials total | $9,200 U |
| Direct labor rate variance | $9,500 U |
| Direct labor efficiency variance | $10,000 F |
| Direct labor total | $500 F |
| Variable overhead spending variance | $1,900 U |
| Variable overhead efficiency variance | $2,000 F |
| Variable overhead total | $100 F |
| Fixed overhead budget variance | $2,000 F |
| Fixed overhead volume variance | $10,000 U |
| Fixed overhead total | $8,000 U |
| Total cost variance | $16,600 U |
The cost components produce the same $16,600 U as actual cost of $406,600 less standard allowed cost of $390,000.
| Corrected sales bridge | Amount |
|---|---|
| Budget sales | $620,000 |
| Price variance | $39,000 U |
| Sales volume variance at budget mix | $124,000 F |
| Sales mix variance | $6,000 F |
| Actual sales | $711,000 |
| Net sales variance | $91,000 F |
The sales bridge reaches $711,000, and its components produce the $91,000 F net variance.
Changed quantities and product mix
The smaller report changes the material quantity and the product mix. The prepared results retain three errors.
| Prepared item | Source facts | Prepared result |
|---|---|---|
| Direct materials price | 19,500 kg actual at $5.20; standard price $5 | $4,000 U |
| Direct materials quantity | 19,500 kg actual; 20,000 kg allowed at $5 | $2,500 U |
| Sales mix | Actual A 6,500 and B 5,500; flexed A 7,200 and B 4,800 | $21,000 U |
The changed quantities separate the price base from the usage base. The changed mix separates product mix from total volume.
Practice
Using the changed material facts, which direct materials quantity variance is correct?
With actual sales of 6,500 units of A and 5,500 units of B, what is the sales mix variance at budget prices?
The source ledger correctly records the changed material quantities and prices, but the worksheet has a wrong variance label. Is a correcting journal entry needed?
Change only the base-case actual sales units to 7,500 of A and 4,500 of B, while actual prices are $48 for A and $75 for B. What is the sales mix variance?
Recompute, reconcile, and investigate variances
- Recompute each variance from the input base that caused it, not from the final total.
- Keep U/F signs visible through subtotals and reconcile every bridge to actual minus budget.
- Use the largest differences to ask about purchasing, waste, labor time, overhead spending or capacity, and product mix.
Unlock the full lesson and continue reading
Signup to continue reading this lesson and unlimited access questions, flashcards, AI notes, and more