Future cash flows need discounting
A project requires $100,000 now and returns $60,000 at the end of year 1 and $60,000 at the end of year 2, with a required return of 10%.
A quick subtraction gives $120,000 - $100,000 = $20,000.
That answer is wrong because future money is worth less today.
Each receipt must be discounted before it is compared with the investment.
The first subtraction treats dollars from different dates as equal. The schedule converts each receipt to today's dollars, then measures the value created.
Discount factors, present values and NPV
The schedule moves from the time-0 investment to each future cash flow. It then applies the correct discount period before calculating total value and NPV.
| Line | How it is found | Why |
|---|---|---|
| Initial investment | Given cash paid at time 0 | It is already measured in today's dollars |
| Cash flow in period t | Given receipt or payment | Each period must be handled separately |
| Discount factor for period t | 1 / (1 + r)^t | Converts period-t dollars to today's dollars |
| Present value for period t | Cash flow in period t x discount factor | Measures that receipt today |
| Sum of present values | Add all discounted cash flows | Gives the value of future cash flows today |
| Less: initial investment | Subtract the time-0 cost | Compares value received with value paid |
| Net present value | Sum of present values - initial investment | Measures value added or lost at the required return |
| Check | Sum of PVs - initial investment = NPV | Confirms the schedule ties |
🔑 RULE: Discount each future cash flow by (1 + r)^t. PV = CF_t / (1 + r)^t, and NPV = sum of all PVs - the initial investment. For a stand-alone project, NPV greater than $0 means the project adds value at the required return; NPV less than $0 means it does not.
Here, t is the number of periods until receipt. The variable r is the required return.
For positive future cash flows:
- A higher r lowers each PV and NPV.
- A higher cash flow raises PV and NPV.
- A later receipt lowers PV.
- A higher initial investment lowers NPV.
The Black-Scholes call model is:
$C = S0N(d1) - Ke^(-rT)N(d2)$
$d1 = [ln(S0/K) + (r - q + sigma^2/2)T] / (sigma square root of T)$
$d2 = d1 - sigma square root of T$
Holding all other inputs constant:
- A higher S0 raises call value.
- A higher K lowers call value.
- Higher sigma raises call value.
- A higher r raises call value.
- A higher q lowers call value.
- A longer expected term generally raises call value under the usual no or low dividend assumption.
For fair-value work, fair value is the price that would be received to sell an asset or paid to transfer a liability in an orderly transaction between market participants at the measurement date. NPV acceptance uses $0 as the mathematical decision point, not a GAAP acceptance threshold.
The order matters because time determines the discount factor. The factor determines each PV, and only then can the PVs be summed and compared with the initial cost.
NPV with a 10% required return
The project requires $100,000 now. It pays $60,000 at the end of year 1 and $60,000 at the end of year 2. The required return is 10%.
The schedule below keeps full calculation precision and displays amounts rounded to cents.
| Line | How it is found | Amount |
|---|---|---|
| Initial investment | Given at time 0 | $100,000 |
| Year 1 cash flow | Given at end of year 1 | $60,000 |
| Year 1 discount factor | 1 / (1 + 10%)^1 | 0.909091 |
| Year 1 PV | $60,000 x 0.909091 | $54,545.45 |
| Year 2 cash flow | Given at end of year 2 | $60,000 |
| Year 2 discount factor | 1 / (1 + 10%)^2 | 0.826446 |
| Year 2 PV | $60,000 x 0.826446 | $49,586.78 |
| Sum of PVs | $54,545.45 + $49,586.78 | $104,132.23 |
| Less: initial investment | $104,132.23 - $100,000 | $4,132.23 |
| NPV | Sum of PVs - initial investment | $4,132.23 |
| Check | $104,132.23 - $100,000 | $4,132.23 |
The year 2 receipt has two discount periods, so its discount factor and PV are smaller. The check ties the $104,132.23 PV total to the $4,132.23 NPV.
The NPV changes as the discount rate changes, even when the cash flows stay the same.
Loading diagram…
At 0%, NPV is $20,000. At 10%, NPV is $4,132.23. At 20%, NPV is ($8,333.33).
A higher required return lowers NPV
The initial investment remains $100,000. The year 1 cash flow remains $60,000. The year 2 cash flow remains $60,000. The required return changes to 12%.
The discount factors are shown so the PV, total, NPV, and check lines can be completed.
| Line | How it is found | Amount |
|---|---|---|
| Initial investment | Given at time 0 | $100,000 |
| Required return | Changed fact | 12% |
| Year 1 cash flow | Given at end of year 1 | $60,000 |
| Year 1 discount factor | 1 / (1 + 12%)^1 | 0.892857 |
| Year 1 PV | $60,000 x 0.892857 | ? |
| Year 2 cash flow | Given at end of year 2 | $60,000 |
| Year 2 discount factor | 1 / (1 + 12%)^2 | 0.797194 |
| Year 2 PV | $60,000 x 0.797194 | ? |
| Sum of PVs | Add both PVs | ? |
| Less: initial investment | Subtract $100,000 | $100,000 |
| NPV | Sum of PVs - initial investment | ? |
| Check | Sum of PVs - $100,000 = NPV | ? |
The higher required return lowers both discount factors. It therefore lowers both PVs and the NPV compared with the worked example.
Practice
The year 1 PV is ____.
The year 2 PV is ____.
The sum of the two PVs is ____.
The NPV is ____.
Present value and Black-Scholes inputs
The first question turns on the PV, sum, and NPV lines. The second turns on discount factors and timing. The third turns on the Black-Scholes input rules.
Practice
A project requires $80,000 now and pays $50,000 at the end of year 1 and $50,000 at the end of year 2. If the required return is 10%, what is the NPV?
A project costs $70,000 now, pays $40,000 at the end of year 1 and $40,000 at the end of year 2, and uses an 8% required return. Which single change, with all other facts unchanged, increases NPV?
A Black-Scholes call uses a share price of $50, exercise price of $45, expected term of 3 years, risk-free rate of 4%, expected volatility of 30%, and dividend yield of 1%. Holding every other input constant, which change increases the call's value?
A later receipt lowers present value
Was: The project requires $100,000 now, pays $60,000 at the end of year 1 and $60,000 at the end of year 2, and uses a 10% required return.
Now: Keep every fact the same, but the second $60,000 receipt arrives at the end of year 3. Which schedule lines move, and which way?
Answer: The time index changes from year 2 to year 3. Its discount factor falls from 0.826446 to 0.751315, and its PV falls from $49,586.78 to $45,078.14. The year 1 PV remains $54,545.45, while total PV falls from $104,132.23 to $99,623.59 and NPV falls from $4,132.23 to ($376.41). The $100,000 initial investment does not move.
The rate stayed fixed, but the second receipt moved later. The changed exponent lowers only the second receipt's discount factor and PV.
Discounted cash flow calculation order
The calculation follows a fixed order. Each line supplies the amount needed by the next line.
- List the initial investment, each future cash flow, its date, and the required return.
- Assign each receipt its period t.
- Calculate 1 / (1 + r)^t for each period.
- Multiply each cash flow by its discount factor to get its PV.
- Add the PVs.
- Subtract the initial investment to get NPV.
- Check that the PV total minus the initial investment equals NPV.
- For positive cash flows, a higher rate or later receipt lowers value, while a higher cash flow raises value. For a Black-Scholes call, share price, volatility, risk-free rate, and generally expected term raise value, while exercise price and dividend yield lower it.
The check confirms that the PV total minus the initial investment equals NPV. When several projects must be compared using NPV, payback, EVA, or IRR, continue to Ranking investments with payback, IRR and EVA.