Comparing mutually exclusive choices
Management compares three mutually exclusive choices at present value. Target A has $2,100,000 of operating cash flows and $400,000 of synergies, less a $1,700,000 cash price and $100,000 of transaction costs. Project B is $1,950,000 less a $1,500,000 investment, while divestiture is $1,200,000 of sale proceeds plus $300,000 of avoided costs, less $50,000 of selling costs and $1,000,000 of lost cash inflows. The first answer for the acquisition's opportunity cost is often $700,000, but that is the acquisition's own net value, not the highest rejected value of $450,000.
The key distinction is between the value created by the choice and the value given up by making it. Supply, demand, elasticity and inflation explains forces that can change these forecasts; this schedule compares the supplied forecasts.
Calculating each option’s net value
Use present-value amounts at the decision date. Calculate a net value for each option first. For an acquisition, add operating cash flows and synergies, then subtract the cash price and transaction costs. For a divestiture, add sale proceeds and avoided costs, then subtract selling costs and cash flows given up. For another investment, subtract the investment from its cash inflows. Then rank the net values, identify the highest rejected value, calculate the net advantage, and check the tie-out. All choices are mutually exclusive, and only cash flows changed by the decision belong in the schedule.
| Line | How it is found | Why |
|---|---|---|
| Acquisition net value | PV operating cash flows + PV synergies - cash purchase price - transaction costs | Measures value added by buying the target |
| Divestiture net value | Sale proceeds + PV avoided costs - selling costs - PV cash flows given up | Measures value added by selling the division |
| Alternative investment net value | PV investment cash inflows - investment | Measures value added by another use of funds |
| Rank the options | Order net values from highest to lowest | Shows which choice creates the most value |
| Opportunity cost | Highest net value among rejected options | Measures the best opportunity forgone |
| Net advantage of the selection | Selected net value - opportunity cost | Shows the value advantage over the best rejected choice |
| Check | Selected net value = net advantage + opportunity cost | Proves the schedule ties |
🔑 RULE: Opportunity cost is the value of the next-best alternative forgone when a decision is made. For mutually exclusive choices, use the highest net value among rejected options, not the selected option's own net value and not the sum of all rejected options.
The net value comes before opportunity cost because rejected choices must be compared on the same net basis.
Target A, Project B and Division D
Use the decision facts as present-value amounts. Target A has $2,100,000 of operating cash flows, $400,000 of synergies, a $1,700,000 cash price, and $100,000 of transaction costs. Project B has $1,950,000 of inflows and requires a $1,500,000 investment. Division D has $1,200,000 of sale proceeds, $300,000 of avoided costs, $50,000 of selling costs, and $1,000,000 of lost cash inflows.
| Line | How it is found | Amount | Why |
|---|---|---|---|
| PV of Target A operating cash flows | Fact supplied | $2,100,000 | Benefit from operating the acquired target |
| PV of Target A synergies | Fact supplied | $400,000 | Extra benefit from combining the businesses |
| Target A cash purchase price | Fact supplied | ($1,700,000) | Cost to acquire the target |
| Transaction costs | Fact supplied | ($100,000) | Incremental acquisition cost |
| Acquisition net value | $2,100,000 + $400,000 - $1,700,000 - $100,000 | $700,000 | Net value created by acquisition |
| Project B net value | $1,950,000 - $1,500,000 | $450,000 | Net value of the rejected investment |
| Division D divestiture net value | $1,200,000 + $300,000 - $50,000 - $1,000,000 | $450,000 | Net value of the rejected sale |
| Rank | $700,000 > $450,000 = $450,000 | Acquire Target A | Selected option has the highest value |
| Opportunity cost | Highest rejected net value | $450,000 | Best rejected choice forgone |
| Net advantage | $700,000 - $450,000 | $250,000 | Acquisition value over the best rejected choice |
| Check | $250,000 + $450,000 | $700,000 | Ties to selected acquisition net value |
The acquisition's $700,000 is its selected value, while $450,000 is the value forgone; the $250,000 net advantage plus $450,000 ties to $700,000.
Revised acquisition synergy value
Keep every worked-example fact unchanged except the PV of Target A synergies. The revised synergy estimate is $550,000 instead of $400,000. Calculate the acquisition net value, compare all three choices, identify opportunity cost, calculate net advantage, and complete the check.
| Line | How it is found | Amount | Why |
|---|---|---|---|
| PV of Target A operating cash flows | Fact unchanged from worked example | $2,100,000 | Acquisition operating benefit |
| PV of Target A synergies | Changed fact | $550,000 | Revised combination benefit |
| Target A cash purchase price | Fact unchanged from worked example | ($1,700,000) | Acquisition cost |
| Transaction costs | Fact unchanged from worked example | ($100,000) | Acquisition cost |
| Acquisition net value | Add benefits and subtract acquisition costs | ? | Net acquisition value |
| Project B net value | $1,950,000 - $1,500,000 | $450,000 | Comparison value unchanged |
| Division D divestiture net value | $1,200,000 + $300,000 - $50,000 - $1,000,000 | $450,000 | Comparison value unchanged |
| Rank | Compare the three net values | Use preceding lines | Select the highest value |
| Opportunity cost | Highest rejected net value | ? | Best forgone alternative |
| Net advantage | Selected net value - opportunity cost | ? | Value over the best rejected choice |
| Check | Net advantage + opportunity cost | ? | Must equal selected net value |
A higher synergy estimate changes only the acquisition net value. Project B and the divestiture stay at $450,000 because their facts did not change.
Practice
The revised acquisition net value is ____.
The opportunity cost if Target A is selected is ____.
The revised acquisition's net advantage is ____.
The check amount, equal to net advantage plus opportunity cost, is ____.
Acquisition, opportunity cost and divestiture
These questions turn on the acquisition net-value line, the highest-rejected-value line, and the divestiture net-value line.
The calculations stay in schedule order. Find each option's net value, compare the choices, and identify the value forgone.
Practice
Target A has PV operating cash flows of $2,100,000, PV synergies of $400,000, a cash purchase price of $1,700,000, and transaction costs of $100,000. What is Target A's net acquisition value?
The acquisition has a net value of $700,000, Project B has a net value of $450,000, and the divestiture has a net value of $450,000. If the company selects the acquisition, what is its opportunity cost?
Division D can be sold for $1,200,000, creates $300,000 of PV avoided costs, requires $50,000 of selling costs, and gives up $1,000,000 of PV cash inflows. What is the divestiture's net value?
Three mutually exclusive alternatives have net values of $700,000 for an acquisition, $450,000 for Project B, and $450,000 for a divestiture. If the company selects Project B, what is its opportunity cost?
Assuming a liability with the purchase
Was: Target A had $2,100,000 of PV operating cash flows, $400,000 of PV synergies, a $1,700,000 cash purchase price, and $100,000 of transaction costs. Its net value was $700,000. Project B and the divestiture each had net values of $450,000. The acquisition was selected, with $450,000 of opportunity cost and $250,000 of net advantage.
Now: The buyer also assumes a $200,000 liability in addition to the $1,700,000 cash purchase price. Which schedule lines move, and which way?
Answer: The acquisition's total outlay becomes $2,000,000, so its net value falls from $700,000 to $500,000. Project B and divestiture remain $450,000, so opportunity cost remains $450,000 and net advantage falls to $50,000.
Calculating opportunity cost and net advantage
Use this order:
- Calculate acquisition net value from PV operating cash flows, synergies, purchase price, and transaction costs.
- Calculate divestiture net value from sale proceeds, avoided costs, selling costs, and lost cash flows.
- Calculate each alternative investment's net value from PV inflows less investment.
- Rank all net values from highest to lowest.
- Set opportunity cost equal to the highest net value among rejected options.
- Calculate net advantage as selected net value less opportunity cost.
- Check that selected net value equals net advantage plus opportunity cost.
The check confirms that the selected value equals the value of the best forgone choice plus the value gained by choosing differently.