Learning Outcome Statement
Evaluate the expected return and risks of a yield curve strategy.
On the exam: You get a mandate and benchmark, signed curve exposure, scenario probabilities and yield changes, and implementation constraints. You calculate expected net return, assess risk, and give a mandate recommendation in a constructed response or item set.
Your client is not buying a curve story in isolation. The insurer is paying for active return relative to a benchmark while accepting only the risks and trading burden its mandate permits. The expected net return is $E[R]$, built from carry and roll-down $C$, expected price effect $E[P]$, and implementation cost $K$, all stated as decimal holding-period returns. For scenario $s$, price effect is $P_s$ and total return is $R_s$ with probability $p_s$, while at key-rate point $j$, signed active exposure is $H_j$ and yield change is $\Delta y_{j,s}$.
| Item | What you inspect |
|---|---|
| Carry and roll-down | Holding-period return before costs |
| Price effect | Exposure sign and yield change |
| Implementation cost | Trading and financing drag |
| Active Share | Holdings difference |
| Tracking error | Benchmark-relative active-return volatility |
The benchmark is the reference for active return, the mandate sets how much active risk you may spend, and scenario variance is $\operatorname{Var}(R)$. The formula keeps the return source, curve view, implementation drag, and scenario risk separate so you can challenge each one.
$$ \begin{aligned} E[R] &= C + E[P] - K \ P_s &\approx -\sum_j H_j \Delta y_{j,s} \ R_s &= C + P_s - K \ E[P] &= \sum_s p_s P_s \ E[R] &= \sum_s p_s R_s \ \operatorname{Var}(R) &= \sum_s p_s\left(R_s-E[R]\right)^2 \end{aligned} $$
$C$ raises the answer because it is return earned while holding the position. $K$ lowers it because the insurer pays trading and financing drag. A positive $P_s$ helps only in that scenario, and the negative sign makes a negative signed exposure gain when its yield rises. Weighting $R_s$ by $p_s$ gives expected return, while the variance line measures scenario dispersion around that expectation. The approximation omits convexity and spread changes, so forecast and model risk remain in the review.
The portfolio manager states the mandate, benchmark, and active-risk budget before choosing the portfolio action. The execution benchmark is set before the trade is observed. The alpha source is the curve position, and capacity, turnover, liquidity, financing, and transaction cost decide whether implementation preserves it.
Loading diagramā¦
This sequence keeps the alpha source inside the risk budget and prices implementation before approval. Start with the clientās permitted active risk, then test whether the curve position earns enough after trading and financing drag. Scenario weighting translates the view into expected return, while the final review checks whether liquidity, capacity, and forecast uncertainty could prevent that return from reaching the portfolio. The recommendation therefore depends on both the calculated result and the mandate constraints.
.
Scenario dispersion is one risk lens. It does not replace benchmark-relative volatility captured by tracking error. Each bar is a scenario return, and the line is the probability-weighted expected net return, $0.017641$. Read the bars against that common reference: flattening sits above the expectation, steepening sits below it, and the parallel case lies between. The spread shows how sensitive the result is to the assumed curve path, but it does not tell you whether active return volatility breaches the mandateās tracking-error budget. For that, assess benchmark-relative returns separately.
Loading diagramā¦
Compare each outcome with the probability-weighted line before moving to the exact figures. A bar above the line contributes a return greater than the expectation in that case; a bar below it contributes less. The width between the highest and lowest bars describes the range across these three specified scenarios. Use the table to retain each value for calculation, then assess tracking error independently because scenario range is not benchmark-relative volatility.
| Scenario | Return |
|---|---|
| Flatten | $0.018425$ |
| Parallel | $0.017000$ |
| Steepen | $0.015575$ |
The scenario figures show flattening at $0.018425$, parallel movement at $0.017000$, and steepening at $0.015575$. The return range is from $0.015575$ to $0.018425$, with steepening the weakest outcome. Treat that range as a scenario-dispersion check, then compare the separate tracking-error estimate with the active-risk budget. A favorable average cannot compensate for an outcome or implementation constraint that the client has ruled out.
| Risk check | Stress to decision |
|---|---|
| Active-risk budget | Tracking error exceeds limit |
| Level and curve exposure | Active return moves against benchmark |
| Forecast and model risk | View or approximation fails |
| Liquidity and capacity | Trade cannot absorb scale |
| Turnover and financing | Carry is consumed |
| Transaction costs | Net return falls |
Compare these stresses with the mandate's risk budget and forecast tracking error. A positive expected return cannot waive a liquidity, capacity, turnover, financing, or transaction-cost limit.
Worked example
You are advising a USD insurance general-account investor. The benchmark is a USD intermediate Treasury benchmark, and the strategy is short the front key-rate exposure and long the back key-rate exposure. You need expected net return and a recommendation after implementation cost. The mandate includes an active-risk budget, liquidity requirement, capacity limit, turnover limit, and pre-trade execution-benchmark requirement.
| Given | Value |
|---|---|
| Carry and roll-down return | $0.018$ |
| Implementation cost return | $0.001$ |
| Front active exposure | $-0.95$ |
| Back active exposure | $0.95$ |
| Flatten probability | $0.6$ |
| Parallel probability | $0.25$ |
| Steepen probability | $0.15$ |
| Front and back flattening change | $0.002$, $0.0005$ |
| Front and back parallel change | $0.001$, $0.001$ |
| Front and back steepening change | $-0.0005$, $0.001$ |
Yield changes are decimal changes. Each paired entry is front, then back, and the scenario probabilities exhaust the cases. Before calculating, keep the exposure signs attached to their key-rate points; reversing either sign reverses that pointās price contribution. The probability weights apply to scenario outcomes after the signed exposures have produced each price effect.
The carry, price, and cost bars show contributions, and the net bar shows the resulting expected return. Read carry as the main positive contribution, expected price effect as a smaller addition, and implementation cost as a deduction. Their combination gives the net figure, so the chart makes clear why a positive curve forecast alone is not the approval case.
Loading diagramā¦
In the return bridge, carry and roll-down contribute $0.018000$, expected price effect adds $0.000641$, and implementation cost subtracts $0.001000$, leaving expected net return of $0.017641$.
-
Apply the signed exposures to each yield change, because the sign determines who benefits from the move. The displayed price effects are $0.0014$, $0.0000$, and $-0.0014$ for flattening, parallel, and steepening. For flattening, $P_{\mathrm{flatten}}\approx -((-0.95)\times0.002)-(0.95\times0.0005)=0.0014$.
-
Add carry and subtract implementation cost for each scenario, so the return reflects what the insurer keeps. The scenario returns are $0.018425$, $0.017000$, and $0.015575$ for flattening, parallel, and steepening.
-
Weight those returns by their probabilities rather than treating outcomes equally. The expected price effect is $0.000641$, and the expected net return is $0.017641$.
-
Compare the scenario returns with expected return, because dispersion is a risk signal. The range is from $0.015575$ to $0.018425$, with steepening the weakest outcome. This is scenario risk, not automatically tracking error.
-
Run the mandate checks before approval. Review level and curve exposure, forecast and model risk, liquidity, capacity, turnover, financing, and transaction costs against the active-risk budget, benchmark, and pre-set execution benchmark.
The expected net return is $0.017641$, so recommend conditional approval only if the active-risk budget, liquidity, capacity, turnover, financing, transaction-cost, and execution-benchmark checks pass.
Changed condition
You keep the mandate and position unchanged. Only the front yield change in the flattening scenario changes, moving from $0.002$ to $0.003$.
| Measure | Base | Changed |
|---|---|---|
| Front flattening yield change | $0.002$ | $0.003$ |
| Expected price effect | $0.000641$ | $0.001211$ |
| Expected net return | $0.017641$ | $0.018211$ |
Because your front exposure is negative, a larger positive front yield move improves the flattening price effect. The flattening scenario has probability $0.6$, so the expected price effect and expected net return rise while carry, cost, and the other scenario returns stay unchanged. Those unchanged outcomes sit farther below the new average, so your return improves but scenario risk also grows. Before reading on, recalculate the scenario returns and identify which outcome sits furthest below the new expectation.
Common error
You may see a large difference between a portfolio's holdings and its benchmark and call it large tracking error. That feels right because Active Share and tracking error both sound like summaries of active management, but Active Share describes holdings differences while tracking error describes benchmark-relative return volatility. You can spot the mistake when your answer labels the holdings difference as large risk without assessing benchmark-relative return volatility, the mandate's risk budget, capacity, turnover, and execution cost.
Calculator
| Keys | Display |
|---|---|
| 2ND CLR WORK | 0.0000 |
| 0.018 ENTER | 0.018000 |
| 0.000641 ENTER | 0.000641 |
| -0.001 ENTER | -0.001000 |
| CPT NET RETURN | 0.017641 |
Check yourself
Practice
recommend
Recommend whether to approve the strategy and state the implementation conditions.
Which statement best evaluates the strategy's active risk?
Revision snapshot
Expected net return is $E[R] = C + E[P] - K$, which is carry and roll-down plus expected price effect minus implementation costs. Price effect is approximately $-\text{signed key-rate exposure}\times\text{yield change}$. Scenario expected return is the probability-weighted average of scenario returns. Risk review includes level and curve exposure, forecast and model risk, liquidity, capacity, turnover, financing, and transaction costs. Active Share describes holdings difference. Tracking error describes volatility of benchmark-relative active return. On the exam, connect the calculation to the mandate, benchmark, active-risk budget, and pre-set execution benchmark.
Unlock the full lesson and continue reading