Learning Outcome Statement
Explain how the information ratio may be useful in investment manager selection and choosing the level of active portfolio risk.
On the exam: You will receive a benchmark, manager forecasts, tracking errors, and limits on the client's willingness and capacity to take risk. You will then choose a manager or recommend an active-risk level with a short calculation and justification.
You are comparing managers who try to beat a benchmark, not merely ranking their forecast total returns. A manager may forecast more active return by taking much more benchmark-relative risk. You want the manager that offers more expected active return for each unit of active risk, subject to what the client accepts and can bear.
The return above the benchmark is expected active return. The uncertainty around that return is active risk, measured by tracking error. Call the comparison the information ratio, $IR$.
| Quantity | Definition |
|---|---|
| Expected active return | Return above benchmark |
| Active risk | Tracking error |
| Client willingness | Active risk the client accepts |
| Client capacity | Active risk the client can bear |
| Active-risk ceiling | Lower of both limits |
The manager's benchmark-relative forecast goes in the numerator. Expected tracking error goes in the denominator. This is a benchmark-relative measure, not a measure of the portfolio's total risk. The client may accept more risk than the client can bear, so the lower limit sets the active-risk ceiling.
Use $IR$ to compare those forecasts on the same benchmark-relative scale.
$$ \begin{aligned} IR&=\frac{\text{expected active return}}{\text{expected active risk}}\ &=\frac{\text{expected active return}}{\text{expected tracking error}} \end{aligned} $$
| Input that rises | Input held fixed | Effect on $IR$ |
|---|---|---|
| Expected active return | Tracking error | $IR$ rises |
| Tracking error | Expected active return | $IR$ falls |
A larger expected active return raises $IR$ when tracking error is fixed. A larger tracking error lowers $IR$ when active return is fixed. A higher $IR$ means more expected active return per unit of active risk, not necessarily a higher total return. Compare managers only on the same benchmark and risk basis.
A common trap is to choose the manager with the highest expected active return. That feels right because the return forecast is larger. The giveaway is a larger tracking error that leaves the manager with a lower $IR$. Use the manager's $IR$ and the client's active-risk ceiling together.
Scale active risk only when the manager's expected $IR$ and the proportional-scaling assumption remain credible. Under that assumption, expected active return moves in proportion to the selected active risk.
Use this sequence in the vignette.
Loading diagram…
Keep the benchmark comparison separate from the client gate. The manager's $IR$ supports the comparison, while willingness and capacity determine the active risk you can implement. Read the visual from left to right: first identify the benchmark, then compare managers on the same basis. Only after that comparison should you test both client limits. The lower limit controls the final position size, even when the selected manager forecasts more tracking error. This order prevents a strong forecast from overriding an unsuitable risk level.
Worked example
You are on an investment committee choosing an active manager for an investor. The objective is benchmark-relative active return, and both managers use the same benchmark with annual ex ante decimal forecasts. The investor's willingness and capacity have produced an active-risk ceiling of $0.018$. The committee accepts proportional scaling when the chosen manager's expected $IR$ remains credible. Which manager should you choose, and what active risk should you implement?
| Input | Annual decimal |
|---|---|
| Manager A expected active return | $0.012$ |
| Manager A tracking error | $0.04$ |
| Manager B expected active return | $0.009$ |
| Manager B tracking error | $0.02$ |
| Active-risk ceiling | $0.018$ |
The line plots Manager B's expected active return against active risk. The plotted points show proportional scaling, not permission to exceed the client's ceiling. Read each point as a possible scale under the stated assumption: doubling active risk doubles expected active return, so the ratio stays at $0.45$. The table supplies exact values for selected risk levels, while the chart makes their straight-line relationship easier to see. The investor's ceiling still selects the allowable point; the plotted values above it are illustrations only.
Loading diagram…
| Active risk | Expected active return |
|---|---|
| $0.0000$ | $0.0000$ |
| $0.0100$ | $0.0045$ |
| $0.0200$ | $0.0090$ |
| $0.0300$ | $0.0135$ |
- Calculate Manager A's $IR$ because selection compares return per unit of tracking error. Dividing $0.012$ by $0.04$ produces $0.30$.
- Calculate Manager B's $IR$ on the same basis. Dividing $0.009$ by $0.02$ produces $0.45$.
- Compare the ratios before looking at total active return. Manager B is the efficient choice because $0.45$ exceeds $0.30$, even though Manager A forecasts $0.012$ versus Manager B's $0.009$.
- Apply the client constraint. Manager B's forecast tracking error is $0.02$, so scale the position to the ceiling of $0.018$ rather than implement $0.02$.
- Estimate the active return at that scale. The calculation is $0.45 \times 0.018=0.0081$ because the accepted proportional-scaling assumption keeps the expected ratio credible.
Choose Manager B and implement active risk of $0.018$, with expected active return of $0.0081$. The recommendation uses the stronger benchmark-relative efficiency while respecting the investor's binding constraint.
Changed condition
Keep the same managers, benchmark, and investor, but lower the active-risk ceiling. Predict the direction before using the before-and-after view.
| Input | Base case | Changed case |
|---|---|---|
| Active-risk ceiling | $0.018$ | $0.012$ |
| Manager B information ratio | $0.45$ | $0.45$ |
| B active return at ceiling | $0.0081$ | $0.0054$ |
Your prediction should be that a lower ceiling reduces active risk and expected active return while leaving manager efficiency alone. The movement comes from changing implementable scale, not Manager B's forecast skill. The lower client limit remains binding. Recompute Manager B's expected active return at $0.012$ before reading on.
Common error
A candidate chooses Manager A because its expected active return of $0.012$ is higher than Manager B's $0.009$. That feels right because the candidate is treating the forecast, or the information ratio, as a total-return score instead of a per-unit active-risk measure. A benchmark-relative question that supplies tracking error and a client willingness or capacity limit gives it away because you must calculate each ratio first and then reject any active-risk choice above the binding ceiling.
Check yourself
Practice
An investor compares Manager A and Manager B against the same benchmark. Forecasts are annual ex ante decimal values, and the active-risk ceiling is 0.018. The committee accepts proportional scaling for Manager B.
Question 1
Which manager has the higher information ratio?
Question 2
Which active-risk implementation fits the stated ceiling for the selected manager?
Question 3
Assuming proportional scaling remains credible, what expected active return follows for Manager B at active risk 0.018?
Question 4
Which statement best explains why a higher information ratio does not necessarily mean a higher total return?
With the active-risk ceiling reduced to 0.012, what should the investor implement for Manager B, assuming proportional scaling remains credible?
Revision snapshot
Information ratio is $IR=\frac{\text{expected active return}}{\text{expected active risk}}$, where active risk is tracking error. A higher information ratio means more expected active return per unit of active risk, not necessarily a higher total return. Active risk must fit both the client's willingness and capacity, and the binding constraint governs implementation. Scale active risk only when the manager's expected information ratio and the proportional-scaling assumption remain credible. The exam gives a benchmark, manager forecasts, tracking error, and a client limit. Calculate per-unit efficiency first, then check the implementable ceiling. The trap is choosing the highest expected active return or treating the information ratio as a total-return score.
Unlock the full lesson and continue reading
Signup to continue reading this lesson and unlimited access questions, flashcards, AI notes, and more