Learning Outcome Statement
Describe pathwise valuation in a binomial interest rate framework and calculate the value of a fixed-income instrument given its cash flows along each path.
On the exam: You are given a calibrated binomial interest-rate tree, risk-neutral path probabilities, and cash flows along each path. You calculate the arbitrage-free value with a probability-weighted pathwise calculation and round to the stated precision.
At valuation time $t_0$, you value the instrument before any receipts. The tree can give a different one-period rate at different nodes, so a receipt that follows an up node does not face the same financing path as a receipt that follows a down node. You keep that path information by discounting each path separately, then combine the paths with the supplied risk-neutral probabilities.
| Quantity | Notation |
|---|---|
| Valuation time | $t_0$ |
| Path label | $j$ |
| Path probability | $q_j$ |
| Receipt | $CF_{j,t}$ |
| Rate encountered | $r_{j,s}$ |
| Path value | $V_{0,j}$ |
| Instrument value | $V_0$ |
Here, $t$ identifies a receipt date and $s$ walks through the rates before that date. The supplied risk-neutral probability for path $j$ is $q_j$, and keeping $j$ on every input gives that path its own discounted value before the probabilities combine the paths.
The pathwise calculation first gives each path its own discounted value. The instrument value then weights those path values with the supplied probabilities.
$$ \begin{aligned} V_{0,j} &= \sum_t \frac{CF_{j,t}}{\prod_{s=1}^{t}(1+r_{j,s})} \ V_0 &= \sum_j q_j V_{0,j} \end{aligned} $$
The inner sum collects the receipts on one path after discounting each by the growth factors encountered before its payment date. A later receipt carries more factors in the product. The outer sum applies $q_j$ to the already discounted path value and adds all paths. A higher node rate makes $1+r_{j,s}$ larger and lowers the present value of receipts after that node on every path that visits it.
When the tree is already calibrated, use this sequence.
Loading diagram…
Worked example
You are handed a calibrated binomial interest rate tree for a fixed-income instrument valued at $t_0$, immediately after a coupon date. You need its arbitrage-free value from the investor perspective. The tree supplies path probabilities and cash flows along each path. What value should you report?
| Input | Value |
|---|---|
| Valuation time | $t_0$, after coupon date |
| Periods | 2 annual periods |
| Face value | USD 100 |
| Coupon | USD 4 per annual period |
| Common first-period rate | 0.04 |
| Up-node rate | 0.06 |
| Down-node rate | 0.02 |
| Up-node paths | $UU$, $UD$ |
| Down-node paths | $DU$, $DD$ |
| Path probability | 0.25 each |
| Perspective | Investor, positive receipts |
| Rate basis | Effective one-period annual decimals |
These inputs describe one tree and four possible two-period paths. The first rate is shared, but the second rate depends on whether the path reaches the up node or the down node. The equal probabilities apply to paths, not directly to individual receipts. Keep those roles separate as you build the valuation: rates determine each path's discount factors, while probabilities determine how much each completed path contributes to the instrument value.
The investor receipts are:
| Period | Cash flow |
|---|---|
| First annual date | USD 4 |
| Second annual date | USD 104.00 |
The first receipt is the coupon, and the second combines the coupon with face value. Because the receipts arrive at different dates, discount them with the number of periods each one has actually passed through. The first-date coupon uses only the common first-period rate. The final payment uses both the common rate and the rate at that path's second-period node. This distinction preserves the timing of the cash flows and the rate history of each route through the tree.
Call the common first-period rate $r_0$. The up-node rate is $r_u$. The down-node rate is $r_d$. Call the product of growth factors on path $j$ $D_j$.
-
Turn each rate into a growth factor because each period contributes one factor. The outputs are $1+r_0=1.0400$, $1+r_u=1.0600$, and $1+r_d=1.0200$.
-
Multiply the factors along each path because the final receipt passes through both periods. The outputs are $D_{UU}=D_{UD}=1.1024$ and $D_{DU}=D_{DD}=1.0608$.
-
Discount the two receipts separately because they arrive at different dates. For $UU$ and $UD$, the path value is $V_{0,UU}=V_{0,UD}=\frac{4}{1.0400}+\frac{104.00}{1.1024}=98.19$.
-
Use the down-node product for $DU$ and $DD$. Their path value is $V_{0,DU}=V_{0,DD}=\frac{4}{1.0400}+\frac{104.00}{1.0608}=101.89$.
-
Weight each path value by its supplied risk-neutral probability. The up-node paths contribute $0.25 \times 98.19=24.55$ each, and the down-node paths contribute $0.25 \times 101.89=25.47$ each.
-
Add all weighted contributions because the instrument includes every path. The result is $V_0=24.55+24.55+25.47+25.47=100.04$.
The arbitrage-free value is USD 100.04. Use it as the tree's benchmark when comparing the model value with a quoted price.
Changed condition
The same instrument is stressed by changing only the up-node rate. All other inputs, path probabilities, and receipts stay as stated. Predict the new value before reading the comparison.
| Measure | Before | After |
|---|---|---|
| $t_1$ up-node rate | 0.06 | 0.08 |
| $UU$ and $UD$ path value | USD 98.19 | USD 96.44 |
| Arbitrage-free value | USD 100.04 | USD 99.16 |
Predict a lower value before looking at the last column. The larger up-node rate makes the second-period denominator for paths $UU$ and $UD$ larger, so their final receipt is worth less. Paths $DU$ and $DD$ keep their old rate product, and unchanged probabilities leave the total lower. Before reading on, calculate the new $UU$ path discount product yourself.
Common error
A candidate discounts every receipt using one common yield or carries the same second-period rate across every path because the instrument has one set of cash flows. That feels right because ordinary bond pricing often starts with one quoted yield, and one rate makes the arithmetic look familiar. The supplied node-specific rates and risk-neutral path probabilities give it away, so each path must use its own product of discount factors before you weight the path values.
Calculator
Enter each weighted path contribution, then compute their sum.
| Keys | Display |
|---|---|
| 0.25 x 98.19 = M+ | 24.55 |
| 0.25 x 98.19 = M+ | 24.55 |
| 0.25 x 101.89 = M+ | 25.47 |
| 0.25 x 101.89 = M+ | 25.47 |
| CPT SUM | 100.04 |
Check yourself
Practice
A fixed-income instrument is valued at t_0 immediately after a coupon date. It pays USD 4 at the first annual date and USD 104.00 at the second annual date. The common first-period rate is 0.04, the up-node rate is 0.06, the down-node rate is 0.02, and paths UU, UD, DU, and DD each have supplied risk-neutral probability 0.25.
Question 1
For path UU, what is the discounted path value?
Question 2
Which discount product applies to path DU?
Question 3
Which approach gives the arbitrage-free value?
Question 4
What is the arbitrage-free value for the stated tree?
If the t_1 up-node rate changes to 0.08 while the other supplied inputs stay unchanged, what is the arbitrage-free value?
Revision snapshot
For each path, discount each receipt by the product of the rates for the periods encountered on that path. The calculation uses the corresponding growth factors $1+r_{j,s}$.
$$ V_0=\sum_j q_j\left(\sum_t \frac{CF_{j,t}}{\prod_{s=1}^{t}(1+r_{j,s})}\right) $$
Pathwise value = probability-weighted sum of the discounted values along all paths. Use the risk-neutral path probabilities supplied with the arbitrage-free tree. A higher node rate lowers the present value of receipts on every path that visits that node. When node-specific rates are supplied, never use a common yield or reuse a rate from a later period.
Unlock the full lesson and continue reading