Learning Outcome Statement
Interpret changes in a credit spread.
On the exam: The vignette gives settlement, cash-flow, yield-convention, curve and spread information, then asks for the price or risk-measure effect and a concise interpretation in a calculation or item-set format.
A corporate bond promises the same coupons and principal after the spread moves. The spread is not an extra cash payment. Start with the matched-maturity risk-free rate, $r$. Add the credit spread, $s$, to reach the investor’s required yield, $y$. You care because a wider spread changes the discount rate applied to fixed cash flows.
| Convention | Stated condition |
|---|---|
| Credit spread, $s$ | Corporate yield minus matched-maturity risk-free yield |
| Settlement | Immediately after coupon date |
| Accrual | Zero |
| Price | Clean price equals dirty price |
| Yield | Annual decimal rates |
| Compounding | Annual |
| Periods per year | $1$ |
| Curve move | Risk-free curve unchanged |
| Optionality | Option-free bond |
These conditions isolate the spread move, so a wider $s$ raises $y$ without changing promised cash flows. Zero accrual makes clean and dirty price equal, while an embedded option or a moving risk-free curve would add another price effect.
With annual coupons, the coupon, $C$, arrives at each period $t$. Face value, $F$, returns at the last of $n$ annual periods. Price, $P$, is the present value of those cash flows. Spread duration, $D_s$, links the percentage price change $\Delta P/P$ to the spread change $\Delta s$.
$$ \begin{aligned} y &= r+s \ P &= \sum_{t=1}^{n}\frac{C}{(1+y)^t}+\frac{F}{(1+y)^n} \ \frac{\Delta P}{P} &\approx -D_s\Delta s \end{aligned} $$
Start with $y=r+s$. If $r$ is fixed, a wider $s$ raises the yield the investor demands. Each denominator then grows, so every future cash flow is worth less and $P$ falls. A narrowing spread lowers $y$ and raises $P$ under the same assumptions. The minus sign in the duration approximation says the same thing, and a larger $D_s$ means a larger price response for the same $\Delta s$.
Use this order when the vignette mixes curve, spread, settlement and optionality facts.
Loading diagram…
The decision path keeps the assumptions in view before you interpret the picture of the transaction. Confirm that the risk-free curve is unchanged, settlement creates no accrued interest, and the bond has no embedded option. Then trace the promised coupon and principal payments between issuer and investor. This separation lets you attribute the valuation change to the spread and required yield alone.
Read the cash-flow path from the bond outward. The issuer promises coupons and principal, while the investor supplies the purchase price and later receives those amounts. The spread changes the yield used to value this exchange; it does not alter the promised payments. With the risk-free curve fixed and no option, isolate the price effect by changing only the spread.
Worked example
You are handed a three-period annual-pay, option-free corporate bond. Settlement is immediately after a coupon date, the risk-free rate is $0.03$, and the credit spread moves from $0.01$ to $0.02$ while the cash flows stay fixed. What are the new required yield, price change, and approximate spread duration?
Before calculating, separate the inputs that define the bond from the rates used to discount it. Face value, coupon rate and maturity determine the promised cash flows. The risk-free rate and spread combine into required yield. Settlement and annual compounding determine how those flows are timed and valued. Holding the curve fixed makes the spread change the only rate shock in this example.
| Given | Value |
|---|---|
| Face value | USD 100 |
| Coupon rate | $0.05$ annually |
| Risk-free rate | $0.03$ annually |
| Original spread | $0.01$ |
| New spread | $0.02$ |
| Maturity | $3$ annual periods |
| Settlement | Immediately after coupon date |
| Accrual | Zero |
| Yield convention | Annual compounding |
| Periods per year | $1$ |
| Curve assumption | Risk-free curve unchanged |
| Optionality | Option-free |
| Curve yield $0.0400$ | USD 102.78 |
| Curve yield $0.0500$ | USD 100.00 |
| Curve yield $0.0600$ | USD 97.33 |
| Curve yield $0.0700$ | USD 94.75 |
The price falls as required yield rises across these points. These values show the direction and scale of the response for the stated annual cash flows: USD 102.78 at 0.0400, USD 100.00 at 0.0500, and progressively lower prices at higher yields. Use the chart to check the direction after calculating, while keeping the spread move distinct from any change in the risk-free curve.
Loading diagram…
The investor receives this cash-flow schedule. Each of the first two periods pays only the annual coupon, calculated from face value and the coupon rate. At maturity, the investor receives both the final coupon and repayment of face value. Discounting each amount at the required yield produces the bond price, so the schedule makes clear which payments remain fixed as the spread changes.
| Period | Cash flow | Investor sees |
|---|---|---|
| $1$ | USD 5.0000 | Coupon to investor |
| $2$ | USD 5.0000 | Coupon to investor |
| $3$ | USD 105.00 | Coupon and face value |
- Calculate the annual coupon from the face value and coupon rate. $C=0.05 \times 100=5.0000$. This produces USD 5.0000 in the early periods and USD 105.00 at maturity.
- Call the starting required yield $y_0$ and add the original spread to the risk-free rate. This gives $y_0=0.03+0.01=0.0400$.
- Call the new required yield $y_1$. Adding the new spread gives $y_1=0.03+0.02=0.0500$, so the discount rate rises.
- Discount the schedule at $y_0$, because this gives the pre-move price. The substitution $\frac{5.0000}{1.0400}+\frac{5.0000}{(1.0400)^2}+\frac{105.00}{(1.0400)^3}$ produces $P_0=102.78$.
- Discount at $y_1$ to isolate the spread move. The substitution $\frac{5.0000}{1.0500}+\frac{5.0000}{(1.0500)^2}+\frac{105.00}{(1.0500)^3}$ produces $P_1=100.00$.
- Measure the move, because direction alone does not quantify spread risk. The spread change is $\Delta s=0.0100$, the price change is $\Delta P=-2.78$, the decimal percentage price change is $\Delta P/P_0=-0.0270$, and the approximate spread duration is $D_s=2.70$ years.
The bondholder should mark the option-free bond down by USD 2.78, from USD 102.78 to USD 100.00, and read 2.70 years as the approximate spread sensitivity.
Changed condition
Now change only the new spread to $0.03$ while keeping the face value, coupon, curve, settlement and optionality unchanged. Predict the new required yield and price before looking at the comparison.
| Measure | Before | After |
|---|---|---|
| Credit spread | $0.0200$ | $0.0300$ |
| Required yield | $0.0500$ | $0.0600$ |
| Price | USD 100.00 | USD 97.33 |
You should have predicted the after column. The extra spread lifts required yield and lowers price because the cash flows and risk-free curve did not move. The table shows the spread moving from $0.0200$ to $0.0300$. The price change is $\Delta P=-5.45$, the decimal percentage price change is $-0.0530$, and the proxy spread duration is $2.65$ years. Before reading on, state the curve, settlement and optionality assumptions, then predict the price direction for a spread narrowing.
Common error
A candidate sees the spread widen and adds the wider spread to the bond’s return, then records a positive price change. That feels right because a larger spread sounds like extra compensation paid to the investor. A positive price change for an option-free bond when the risk-free curve and cash flows are unchanged gives it away, because the required yield rose and price should have fallen.
Check yourself
Practice
A three-period annual-pay, option-free corporate bond has face value USD 100, coupon rate 0.05, risk-free rate 0.03, and current credit spread 0.02. Its original spread was 0.01. Settlement is immediately after a coupon date, accrual is zero, compounding is annual, periods per year is 1, and the risk-free curve remains unchanged.
Question 1
What is the bond's current required yield?
Question 2
If the credit spread widens while the risk-free curve and cash flows remain unchanged, what happens to an option-free bond's price?
Question 3
Using the stated annual convention, what is the bond's current price?
Question 4
Using the original and current prices, which approximate spread duration follows?
For the same option-free bond, with the risk-free curve, cash flows, settlement and optionality unchanged, the credit spread rises from 0.02 to 0.03. Which pair gives the new price and approximate spread duration?
Revision snapshot
Credit spread $=$ corporate yield $-$ matched-maturity risk-free yield. For an option-free bond, spread widening increases required yield and lowers price, all else equal. Approximate spread duration says percentage change in price $\approx -D_s\Delta s$.
Interpret spread changes only after stating the curve-move assumption, settlement and accrual convention, and optionality. The trap is treating a wider spread as a positive return contribution and reporting a positive price change. On the exam, state the assumptions, calculate the required yield, price or risk measure, and give the direction.
Unlock the full lesson and continue reading
Signup to continue reading this lesson and unlimited access questions, flashcards, AI notes, and more