Learning Outcome Statement
Describe principles of capital allocation and common capital allocation pitfalls.
On the exam: You get a short project fact pattern with incremental cash flows and governance details, then choose the sound capital-allocation principle or exposed pitfall in a single-best-answer or structured matching format.
You are deciding whether a project deserves the firm's scarce capital. The project is judged by the cash it changes, not by cash already spent or by the way the firm finances it. From the firm's perspective, a payment is negative and a project receipt is positive. A governance check matters because a positive value screen can rest on weak assumptions or poor accountability.
| Allocation point | Sound treatment | Pitfall exposed |
|---|---|---|
| Incremental cash flows | Include cash changed by project | Use total company cash |
| Sunk costs | Exclude paid costs | Let past spending drive choice |
| Opportunity costs | Include forgone alternative use | Treat owned resources as free |
| Working capital | Include investment and recovery | Omit terminal reversal |
| Operating cash flows | Keep separate, after tax | Mix them with financing cash flows |
| Financing cash flows | Exclude from project cash flow | Subtract borrowing effects twice |
| Nominal cash flows | Match a nominal rate | Mix inflation bases |
| Project risk | Match the project-risk rate | Apply firm WACC automatically |
| Governance checks | Check strategic fit, assumptions, risk, accountability, flexibility | Approve a headline forecast |
An opportunity cost is real without a cash payment, while a sunk cost cannot be changed by accepting the project. Working capital is an outflow while tied up and a cash inflow when released, and after-tax cash flows need an appropriate post-tax rate on the same nominal basis rather than an automatic firm WACC.
At time zero, the project's incremental cash flow is $CF_0$. At a later period $t$, the project produces $CF_t$. Use $r$ for the annual discount rate that matches project risk. The final period is $T$. These inputs form the compact NPV screen.
$$ \mathrm{NPV}=CF_0+\sum_{t=1}^{T}\frac{CF_t}{(1+r)^t} $$
Here, $CF_0$ is usually negative because the firm pays first. Each future $CF_t$ is divided by a factor that grows with time and $r$, so later cash contributes less today. A higher $r$ lowers each future inflow's present value, while terminal salvage and working-capital recovery raise the final cash flow. Financing cash flows stay outside this project screen because the project discount rate supplies the required return, and a positive NPV passes the value screen but not the whole approval process.
Use this sequence before trusting the result.
Loading diagram…
Ask whether the project fits strategy, whether assumptions have evidence, who is accountable for risk and delivery, and where flexibility permits a review or stop decision. That check protects capital when a precise forecast hides weak control.
Worked example
You are handed a project proposal from the firm's perspective. Equipment, the warehouse opportunity cost, and working capital create time-zero commitments, while operating cash arrives before terminal recovery. The feasibility study was already paid, so it is sunk. You need the project's NPV using the nominal, post-tax project rate.
| Given | Amount or treatment |
|---|---|
| Equipment outlay | USD 100 million at time zero |
| Warehouse opportunity cost | USD 15 million at time zero |
| Working-capital investment | USD 10 million at time zero |
| Operating cash flow | USD 45 million after tax, years 1 and 2 |
| Terminal salvage | USD 20 million after tax, year 3 |
| Working-capital reversal | USD 10 million in year 3 |
| Feasibility study | Sunk, exclude |
| Forecast basis | Nominal cash flows |
| Project discount rate | $0.1$ decimal per year, nominal post-tax basis |
| Financing cash flows | Excluded from project screen |
The input list distinguishes cash paid now from cash received later. Equipment, the warehouse's alternative use, and working capital all reduce value at time zero, even though only equipment requires a direct purchase. The study does not enter the calculation because it is already paid. The forecast basis and project rate also belong together: both are nominal and post tax.
Read the sequence from left to right: the firm commits capital first, receives operating cash in the intervening years, then collects salvage value and releases working capital at the end. That final recovery is a real inflow, not a reduction to the earlier investment. The period-by-period schedule below makes the timing visible and shows how discounting translates each amount into value today.
| Period | Cash flow | Present value |
|---|---|---|
| 0 | USD -125.00 million, initial outflow | USD -125.00 million |
| 1 | USD 45.00 million, after-tax operations | USD 40.91 million |
| 2 | USD 45.00 million, after-tax operations | USD 37.19 million |
| 3 | USD 75.00 million, terminal cash flow | USD 56.35 million |
The terminal row combines operating cash, terminal salvage, and working-capital recovery.
- Add the equipment outlay, warehouse opportunity cost, and working-capital investment because each is incremental at time zero. This produces a total initial outflow of USD 125.00 million.
- Add year-three operating cash, salvage, and working-capital recovery because terminal reversals belong in the final cash flow. This produces terminal cash flow of USD 75.00 million.
- Use the project discount rate because the forecast is nominal and post tax and the project's risk sets the rate. The one-period accumulation factor is 1.1000. Discounting the cash flows across periods 1, 2, and 3 produces present values of USD 40.91 million, USD 37.19 million, and USD 56.35 million.
- Combine the negative opening cash flow with those present values because NPV measures net value at time zero. The substitution is shown below.
All terms below are USD millions.
$$ \mathrm{NPV}=-125.00+40.91+37.19+56.35=9.45 $$
The project produces NPV of USD 9.45 million, so it passes the value screen before governance approval.
Changed condition
Keep every input above except the project discount rate. Raise the decimal rate from $0.1$ to $0.15$ per year because the project now carries higher risk.
| Measure | Before | After |
|---|---|---|
| Project discount rate | $0.1$ | $0.15$ |
| Period 1 present value | USD 40.91 million | USD 39.13 million |
| NPV | USD 9.45 million | USD -2.53 million |
Before you looked at the right column, you should have predicted a fall in every future present value because the cash flows stayed unchanged while the project rate rose. The period-one present value moves from USD 40.91 million to USD 39.13 million, and NPV moves from USD 9.45 million to USD -2.53 million. The later terminal cash flow also loses present value, so a rate change can reverse the decision without changing operations. Before reading on, say why the firm's WACC may be wrong for this project.
Common error
You may apply the firm's familiar WACC, its weighted average cost of capital, to every project because one company-wide rate feels objective and consistent. It feels sensible, but you are pricing the firm's risk instead of the project's risk, even when the new project is more or less uncertain than the firm. The giveaway is a project-risk fact pattern, so use a discount rate that reflects the project's risk rather than the financing mix alone.
Calculator
| Keys | Display |
|---|---|
| 2ND CLR WORK | 0.00 |
| 125 +/- CF0 | -125.00 |
| 45 CFJ | 45.00 |
| 45 CFJ | 45.00 |
| 75 CFJ | 75.00 |
| 10 I/Y | 10.00 |
| CPT NPV | 9.45 |
Check yourself
Practice
A project uses an existing warehouse and has a paid feasibility study. Which treatment follows capital-allocation principles?
Revision snapshot
The compact screen is
$$ \mathrm{NPV}=CF_0+\sum_{t=1}^{T}\frac{CF_t}{(1+r)^t} $$
Evaluate projects using incremental cash flows and the discount rate appropriate for project risk. Exclude sunk costs and include opportunity costs. Include working-capital recovery and other terminal reversals. Keep operating cash flows separate from financing cash flows. Match nominal cash flows with a nominal discount rate and post-tax cash flows with an appropriate post-tax rate. Use governance checks for strategic fit, assumptions, risk, accountability, and flexibility. A familiar firm WACC used for every project can hide a project-risk mismatch. On the exam, identify the changed cash, the rate basis, and the governance failure before choosing the answer.